Target cost for construction
Target costs are generally associated with cost-reimbursable contracts. They introduce a mechanism enabling the contractor, and sometimes the consultant team, to share in the benefits of cost savings, but also to bear some of the client's cost when there are cost overruns. Contracting the contractor and the consultant team on a target cost basis can be an effective way of ensuring good collaboration.
The target cost is set early in the project, and then cost savings or overruns are shared based on an agreed formula. The aim is to provide a financial incentive encouraging cost control, rather than to penalise. Bonus and penalty payments are usually capped to prevent over-zealous or adversarial behaviour.
Target costs might be set for the overall project, or for specific elements of the works. Agreeing the target cost requires that the client has sufficient knowledge and experience to be able to accurately estimate the likely cost of the works and to negotiate effectively with the contractor and sometimes the consultant team.
Examples of target cost contracts include the New Engineering Contract (NEC) Engineering and Construction Contracts Option C: Target contract with activity schedule and Option D: Target contract with bill of quantities.
NB: According to NRM2: Detailed measurement for building works, in the context of bills of quantities, the term ‘cost target' means; '...the total expenditure for an element or
work package.'
[edit] Related articles on Designing Buildings
- Bill of quantities.
- Construction contract.
- Contract condition.
- Contract sum.
- Cost overruns.
- Cost-reimbursable contract.
- Disallowed cost.
- Fast-track construction.
- Fixed price contract.
- Force account work.
- Guaranteed maximum price.
- Lump sum contract - pros and cons.
- New Engineering Contract.
- Open-book accounting.
- Procurement route.
- Target contract.
[edit] External references
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.